Batsweledi (Dwaalboom)

Batsweledi (Dwaalboom)

The new 1 million tonne per annum Dwaalboom clinker production line was successfully commissioned at the end of September 2008. After a very successful production ramp up, the kiln was performance tested and handed over to the Dwaalboom Operations team in early December 2008. According to F L Smidth, the kiln and ancillary equipment supplier, this was one of the quickest commissioning, performance testing and handover activities that they have been involved in.

The project team is assisting Dwaalboom Operations with shutdown and guarantee issues and project close out is now underway. The construction village that was built to house the construction contractors is closed and the mothballing process is in progress.

Timeline Gallery

Please scroll over the images below to obtain project progress detail.


October 2008

August 2008

July 2008

June 2008

May 2008

April 2008

March 2008

February 2008

January 2008

November 2007

October 2007

September 2007

August 2007

July 2007

June 2007

May 2007

April 2007

March 2007

February 2007

January 2007

December 2006

November 2006

October 2006

September 2006

August 2006

July 2006

June 2006

May 2006

April 2006

March 2006

February 2006

January 2006

December 2005

November 2005

October 2005

September 2005

August 2005

July 2005